Main Power Transformer Installed at ENNA Group’s Mihăilești Solar + BESS Project

ENNA Group’s Investment in Romania

Date publishedNovember 25, 2026

Zagreb, 24 November 2026 - Another important milestone has been achieved at ENNA Group’s Mihăilești project in Romania with the successful delivery and installation of the main power transformer manufactured by KONČAR D&ST.

The 80 MVA transformer has a total mass of approximately 86 tonnes, including around 16.5 tonnes of insulating oil. For transport, it measured roughly 6.6 × 2.6 × 3.6 metres and weighed about 62.5 tonnes without oil. It travelled from Zagreb to the project site, where it was installed using the Jack&Slide method: the unit is raised with hydraulic jacks and then slid horizontally into its final position on the foundation. It now forms a key part of the project’s grid connection infrastructure.

The transformer will enable the integration of renewable electricity generated by the solar power plant into the transmission network and represents one of the major components of the project’s energy infrastructure.

Located approximately 25 kilometres southwest of Bucharest, the Mihăilești project combines an 87.5 MWp solar power plant, a 70 MW / 140 MWh battery energy storage system (BESS), and the associated grid connection infrastructure. Once operational, the project will contribute to greater grid flexibility and support the integration of renewable energy into the Romanian power system.

With the transformer now in place, works on the solar power plant are nearing completion, while delivery of the BESS equipment is expected in December. Following commissioning activities, the entire project is scheduled to enter commercial operation in April 2027.

Mihăilești marks an important step in ENNA Group’s international expansion and the continued growth of its energy business across Central and South-Eastern Europe. By combining renewable power generation, battery storage and grid infrastructure, the project reflects the Group’s approach to developing integrated energy solutions.

The project also builds on ENNA Group’s growing presence in Romania, where the Group is developing a broader portfolio of renewable energy projects. Through investments in solar power and energy storage, ENNA continues to strengthen its position in a rapidly evolving regional energy market while supporting the transition towards a more resilient and sustainable energy system.